Increasing the Power Generation by Raising the Capacity of the Thrust Bearing Oil Cooling System in Hydroelectric Power Plants

MakaleYalnız künyeScopus SJRQ3
  • SDG 7 · Erişilebilir ve Temiz Enerji
  • SDG 9 · Sanayi, Yenilikçilik ve Altyapı
  • SDG 13 · İklim Eylemi

Özet

Cooling capacity decreases due to faults appearing over time in the thrust bearing oil cooling systems of hydroelectric power plants and cooling process cannot proceed sufficiently. For this reason, while the turbine-generator unit generates energy, the thrust bearing heats up. This temperature problem prevents the unit from operating at full capacity and therefore decreases in energy production. Producing deficient energy in hydroelectric power plants, which is a renewable energy source, causes long-term economic losses for countries. In this study, the thrust bearing cooling system of a vertical Francis turbine, which produces 150 MW of energy per hour, is investigated. The reduction in the cooling capacity over time in turbine thrust bearing cooling system is solved by using exchanger system with additional plate and the power produced by the turbine-generator unit is increased 15 MW/h. This improvement has greatly contributed to the national economy. The method of increasing the cooling capacity applied to the hydroelectric power plant thrust bearings can be applied to all hydraulic turbines. This method will increase the energy production amount of the unit by approximately 10% and it costs approximately 80% cheaper than completely replacing the existing cooling system.

Anahtar Kelimeler

RDL Kalıcı Bağlantı (PID)
https://rdlopen.rawdatalibrary.net/r/munzur/3182Resmi atıflarda kullanılan kalıcı adres
DOI
https://doi.org/10.1007/s11668-020-00969-9Yayıncı resmi DOI adresi
İndeks kayıtları
Kaydın indeks veri tabanlarındaki sayfası (aktarımda alınan kayıt numarasıyla). Erişim, indeksin kendi koşullarına bağlıdır.
Atıflar
Scopus
5
WoS
2
OpenAlex
5
Her kaynağın kendi saydığı toplam atıf; aktarım ve zenginleştirme sırasında alındı.
Tam Kayıt
AlanDeğerDil
dc.contributor.authorKahraman, Gökhan
dc.date.accessioned2026-10-28T14:56:18.559249191Z
dc.date.available2026-10-28T14:56:18.559249191Z
dc.date.issued2020
dc.description.abstractCooling capacity decreases due to faults appearing over time in the thrust bearing oil cooling systems of hydroelectric power plants and cooling process cannot proceed sufficiently. For this reason, while the turbine-generator unit generates energy, the thrust bearing heats up. This temperature problem prevents the unit from operating at full capacity and therefore decreases in energy production. Producing deficient energy in hydroelectric power plants, which is a renewable energy source, causes long-term economic losses for countries. In this study, the thrust bearing cooling system of a vertical Francis turbine, which produces 150 MW of energy per hour, is investigated. The reduction in the cooling capacity over time in turbine thrust bearing cooling system is solved by using exchanger system with additional plate and the power produced by the turbine-generator unit is increased 15 MW/h. This improvement has greatly contributed to the national economy. The method of increasing the cooling capacity applied to the hydroelectric power plant thrust bearings can be applied to all hydraulic turbines. This method will increase the energy production amount of the unit by approximately 10% and it costs approximately 80% cheaper than completely replacing the existing cooling system.
dc.identifier.doi10.1007/s11668-020-00969-9
dc.identifier.eissn1864-1245
dc.identifier.endpage1449
dc.identifier.issn1547-7029
dc.identifier.issue4
dc.identifier.scopus2-s2.0-85089248953
dc.identifier.startpage1445
dc.identifier.urihttps://rdlopen.rawdatalibrary.net/r/munzur/3182
dc.identifier.volume20
dc.identifier.wosWOS:000558893700005
dc.language.isoen
dc.publisherSpringer
dc.relation.ispartofJournal of Failure Analysis and Prevention
dc.rightsinfo:eu-repo/semantics/closedAccess
dc.subjectFailure analysis
dc.subjectHydroelectric power plant
dc.subjectOil cooling system
dc.subjectThrust bearing
dc.subject.classificationEngineering, Multidisciplinary
dc.subject.classificationEngineering
dc.subject.otherCooling
dc.subject.otherCooling systems
dc.subject.otherHydraulic motors
dc.subject.otherHydroelectric generators
dc.subject.otherHydroelectric power
dc.subject.otherLosses
dc.subject.otherThermoelectric equipment
dc.subject.otherThrust bearings
dc.subject.otherTurbogenerators
dc.subject.otherCooling Capacity
dc.subject.otherCooling process
dc.subject.otherEconomic loss
dc.subject.otherEnergy productions
dc.subject.otherNational economy
dc.subject.otherOil cooling system
dc.subject.otherRenewable energy source
dc.subject.otherTurbine generator unit
dc.subject.otherHydroelectric power plants
dc.titleIncreasing the Power Generation by Raising the Capacity of the Thrust Bearing Oil Cooling System in Hydroelectric Power Plants
dc.typeArticle
rdl.citation.openalex5
rdl.citation.scopus5
rdl.citation.wos2
rdl.oa.statusclosed
rdl.scopus.quartileQ3
rdl.sdgSDG07
rdl.sdgSDG09
rdl.sdgSDG13
rdl.source.indexSCOPUS
rdl.source.indexWOS
rdl.wos.indexEmerging Sources Citation Index (ESCI)